EW - East West Petroleum Corporation

  1. 181 Posts.
    East West Petroleum Q3 Results Released November 30th 2020. Information below can be found on Sedar.
    Symbols: EW(Canada) & EWPMF(USA)
    Prices: $0.045CAD & $0.03USD
    Common Shares: 89,585,665
    Website: www.eastwestpetroleum.ca

    Financial Results, Ending September 30th 2020 - keeping in mind that brent oil was lower this quarter

    ASSETS Cash: $4,911,056 - Company currently has a market cap below it's cash value
    GST Receivable: $6,280
    Amounts Receivable: $166,802
    Prepaid Expenses: $28,880
    Investments: $599,200 - Both stocks held have gone up since this end period
    Exploration & Evaluation Assets: $1,655,361
    Property, Plant & Equipment: $368,384
    Total Assets: $7,735,963

    LIABILITIES
    Accounts Payable: $284,094
    Decommissioning: $1,325,303
    Total Liabilities: $1,609,397

    Performance
    Six Month Revenue: $1,135,141 (2019 - $1,491,042) - Lower due to the oil price drop from Covid
    Net Loss: $328,072 - Depletion was $340,000

    Management Discussion Highlights

    New Zealand
    PMP 60291 is the location of the Cheal E-Site and the Cheal E-site production facility as well as the Cheal-E wells.There has been continued positive response from the Cheal E waterflood program, with both production and pressureincreases having been observed. The Cheal E waterflood program was expanded to include the conversion of theCheal-E4 well to a water injector in two Mt. Messenger formation intervals, which has swept oil towards the ChealE1 producing well from the southern area of the field resulting in additional oil recovery and extending the Cheal-Esite’s field life. The Company’s portion of oil and gas production remained relatively consistent during the three months endedSeptember 30, 2020 (“Q2”) compared to the three months ended June 30, 2020 (“Q1). During Q2 the Company’sportion of oil and gas production was 13.8 Mbbl oil and 21.2 Mmcf gas, compared to 15.3 Mbbl oil and 21.8 Mmcfgas during Q1. The Company had five wells, the Cheal-E1, E2, E5, E6 and E8 producing for both Q2 and Q1.On October 24, 2020 the Cheal-E1 pump stopped functioning. The Operator has managed to pull the rods with acrane and intends to clean the well and replace the pump. Production from the Cheal-E1 well is expected to resumeby mid to late December 2020.

    Romania
    As operator, NIS has proposed and is actively progressing comprehensive exploration programs in the EX-2, EX-3,EX-7 and EX-8 exploration blocks in Romania. It should be noted that all activities are dependent on securing thenecessary government and local approvals.Due to the Covid-19 pandemic the state of emergency a nationwide lockdown was imposed by the Romaniangovernment on March 25, 2020. Consequently, the operator NIS, has temporarily ceased new exploration field activityuntil such time that the lockdown is lifted and social distancing requirements can be safely relaxed. It is expected thatthis will substantially delay the planned 2020 exploration programs in the EX-2, EX-3, EX-7 and EX-8 explorationblocks in Romania. As usual, it should be noted that all activities are dependent on securing the necessary governmentand local approvals.On Block Ex-2, acquisition program of 3D seismic in the amount of 170 Km2 was completed in Q3/2019 (calendar)with processing completed in July 2020. Interpretation is currently underway. The Phase 1 Exploration Period wasextended for another two years and now ends in December 2021.On Block EX-3, processing of the data acquired last year on 223 km2 3D seismic program has been finished andinterpretation of the data has been completed. This work identified several exploration prospects with drillingexpected to commence in 2021 (calendar). The Phase 1 Exploration Period was extended for another two years andnow ends in December 2021.On Block EX-7, an exploration well, Bvs-1000, was drilled in Q1/2019 (calendar) to a total depth of 3,800 meters andencountered several potential hydrocarbon bearing zones as identified on logs. Testing has now been postponed until2021 (calendar). On the Teremia North discovery, the initial discovery well, Teremia-1000 experienced mechanical problems resulting in an inflow of formation water. NIS now plans to recomplete the well as a potential gas producerin either 2021 or 2022. An appraisal well, Teremia-1001, was drilled and completed in Q1/2019 (calendar) and,following initial testing, was placed on long term experimental production in July 2019.On Block EX-8, a second deviated appraisal well, Teremia-1002, was drilled into the extension of the Teremia Northdiscovery. The well was completed and tested in Q4/2019 (calendar) and has subsequently been placed on long termexperimental production.NIS has requested extension of the experimental oil production periods for Teremia-1001 and Teremia-1002 to gathermore performance data.An exploration well, Pesac Sud-1000 was drilled and completed in 3Q/2019 (calendar) two separate intervals weretested in Q4/2019 (calendar). Both tests failed to indicate the presence of hydrocarbons. Future testing of potentiallyprospective shallower zones is being considered for 2021 (calendar).NIS is committed to fulfilling the commitment work programs in all blocks, considering certain legislative changesand being granted appropriate extensions due to the current Covid-19 situation.NIS will be funding 100% of the costs and fully carrying the Company through the commitment work programs ineach of the blocks in return for earning an 85% interest in each licence. A technical meeting is tentatively scheduledfor September 2020 in which NIS is expected to present a proposal for a development phase for which the Companywill be responsible for its 15% interest.

    Investments
    As at September 30, 2020 the Company held 240,000 common shares of Orocobre and 190,000 common shares ofSweet Earth with a total quoted value of $599,200

    Commitments
    The Company’s share of expected exploration and development permit obligations and/or commitments as atSeptember 30, 2020 are approximately $147,000 to be incurred during fiscal 2021 and $1,400,000 over the next fiveyears. The Company may choose to alter the program, request extensions, reject development costs, relinquish certainpermits or farm-out its interest in permits where practical
 
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.