    Imo, I don't think there's any problem with financing, at least for ph II anyway.
    Btw, the BNP facility actually covers 60.28% of the OEL ph II capex.

    Of course the caveat for that is a successful ph II production scenario, at, or better than anticipated. That will ensure revenues/profits and loan servicing can continue, with a smile to everyone's dial.

    Original financing for Galoc ph I was estimated at US$86.4M, but delays in the development program (for a number of different reasons) caused it to blow out to $118 million in the end. That was an increase of 36.6% ($31.6M).

    I hope that scenario doesn't repeat itself for ph II, otherwise there will be financing trouble.
    Let's hope lessons learnt during ph I can mitigate a lot of that risk.

    Btw, I don't think Matt would appreciate being called "matter", even though we all are!
 
watchlist Created with Sketch. Add OEL (ASX) to my watchlist
(20min delay)
Last
1.1¢
Change
0.000(0.00%)
Mkt cap ! $52.74M
Open High Low Value Volume
1.2¢ 1.2¢ 1.1¢ $19.49K 1.708M

Buyers (Bids)

No. Vol. Price($)
13 12087762 1.1¢
 

Sellers (Offers)

Price($) Vol. No.
1.2¢ 1134045 2
View Market Depth
Last trade - 16.10pm 13/09/2024 (20 minute delay) ?
OEL (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.