Fantastic Job, well done Pluton Management team.
Achievements to Date
Commenced Cockatoo Island operations October 2012
Introduced new mining service provider -Watpac Civil and Mining
Removed old Ore Handling Plant (“OHP”), the 100kt ore storage facility and installed /commissioned new OHP
Loaded 1st vessel MV Navios Horizon 13 December 2012
Pluton has shipped nine vessels to date totalling 395Kt DSO with an average grade 60.55%Fe
Mobilised a small and experienced on-site Pluton team
Operating costs are reducing as we progress towards increase tonnages
The first of 3 ships for the month of June left port for China on 9 June 2013
100% Safety record, with no lost time injuries
Established and executed significant ore off take agreements
Proven capability to deliver and revenue stream established
- Forums
- ASX - By Stock
- PLV
- Ann: Investor Presentation
Ann: Investor Presentation , page-3
-
- There are more pages in this discussion • 70 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)