    Before we accuse SDO of downramping maybe we could say there is also a balance with some upramping.

    From GBG Feb 2013 announcement

    • Commissioning and ramp-up to 8Mtpa Stage 1 capacity progressing with no material
    issues encountered

    • Karara’s infrastructure was ramped up within expectations

    • MoorMaster system installed to limit downtime during adverse
    weather

    • The six month commissioning and ramp up plan is progressing in
    line with expectations with no material issues encountered
    • Nameplate capacity 8Mtpa scheduled for April, 2013

    • Key risks being eliminated with each area commissioned
    • Product quality matching expectations – premium concentrate to be
    achieved with final area commissioned

    Operating Cash Cost* Stage One 10Mtpa
    A$/t
    Stage Two 16Mtpa
    A$/t
    Total Operating Cash Cost 72-76 64-68



 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.