ticks almost every box to be a multi bagger, page-54

  1. 1,226 Posts.
    lightbulb Created with Sketch. 116
    My rough calculations are:

    Capex: 18.5 Mio $ Coal Mine + 25 $ Beneficiation Plant = 43.5 Mio $
    Estimated Mining Costs approx. 13 $/t
    Estimated Beneficiation/Processing Costs approx. 12 $/t
    Assumption Logistic Costs 10 $/t (should be lower due to close proximity to infrastructure/local power utilities)
    ------------------------------------------------------------
    Total Costs 35$/t
    China 5500 kcal coal price: approx. 85 $/t
    Profit Margin: 50$/t > 12.5 Mio. $ p.a. based on 0.25 mtpa sales agreement

    Profit sharing pro rata must be taken into account if a JV structure for project realiaztion/funding is going to be established. Given a 50:50 JV-funding structure Moduns possible profit p.a. would be approx. the current market cap. Profits from raw coal sales not included.
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.