The quarterly stated that as at the end of December there was 300,000 tonnes of ore of which 100,000 was the higher grade.
They now say they have 500,000 tonnes but don't specify how much is high grade. From that we can assume that the 100,000 hasn't much changed else they would have told us.
The 200,00 tonne increase over 6 weeks comes out to about 33,000 tonnes a week. That is half the planned mining rate.
Crushing 25,000 tonne a week would use up the 100,000 tonne higher grade stuff in 4 weeks flat. Is all of the 100,000 tonne suitable for DSO though? Most likely not.