only 707m to td

  1. 653 Posts.
    lightbulb Created with Sketch. 16
    ? Setting and cementing of the 13 3/8 inch casing at approximately 590mMD
    ? Setting and cementing of the 9 5/8 inch casing at approximately 1,650mMD
    * Completion of drilling operations at well TD, approximately 2,357mMD

    So only 707m to go, and at an average of 30m/hr (including connections) should see us at TD within 24hrs once we get back drilling.

    After drilling I'm guessing another 24hrs to condition the well and clean up. And maybe a wiper trip. POOH.

    This could be all done by Friday if everything goes to plan.
 