News has been released by KEA that Phase 1 of the PEP 5153 farmout commenced 2nd June and the Puka-2 stage has been completed:
RNS - Puka work over
The pump was replaced and the well is back in production. No flow rates have been published but we may hear more from MEO.
To complete Phase 1 of the farmin Meo still has to undertake:
. a similar work over on Puka-1 to restore productive capacity
. test two intervals in the suspended Douglas-1 well, using the same workver rig, before P&A the well.
. drill a new well, Puka-3, from the same well pad as the producing Puka-1 & 2. Puka-3 will be a deviated well to test a potential sweet spot identified on 3D seismic
At the end of Phase 1 MEO will earn a 30% interest in the Puka field production which, fingers crossed, could increase to 500bpd in a success case. The Puka field is estimated to contain between 3.0 Mbbls (2c) and 10.1 Mbbls (3C).
Source - MEO Farm-in document 7 April 2014
Phase 1 was expected to commence prior to the end of June 2014 so MEO are not hanging about.
#:>))
- Forums
- ASX - By Stock
- MEO
- Puka 2 workover completed
Puka 2 workover completed
-
- There are more pages in this discussion • 16 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
LU7
Discover the strong preliminary feasibility of the Bécancour Lithium Refinery, showcasing resilience in a low pricing environment and a strategic plan to capitalize on future price recoveries