Originally posted by Timbogold
↑
In their Jan14 filing, they stated construction would commence mid 2015 with production 3Q18. However, their revised timeline below states construction Oct16 and full commencement late 2019, which is ~12 months after MLNG.
Of more immediate interest is their Jan14 ann. of a global tender (outsourced) for tolling parties for 5mtpa. As yet, no TAs ann. Nonetheless, worth watching to see how this does progress.
Project Timeline (Anticipated)
October 2014: FERC Pre-filing Letter submitted and FERC issues Notice of Pre-Filing Commencement
December 11, 2014: Public Open House in Cameron
August 2015: Project files Application with FERC
June 2016: FERC issues final Environmental Impact Statement
September 2016: FERC issues Order issuing Certificate and Granting Section 3 Authority
October 2016: FERC issues Authorization to Proceed and construction begins
December 2018: In Service – Partial Commencement of Operations
Late 2019: Full Commencement of Operations
Expand
Are they going public? I emailed them buy no response yet.