Ask them how many times it needed to be put back thru the plant, and what volumes were produced as a consequence, clearly you have NO idea.
The rocket scientist had a module in place capable of only a 7 second regrind, Whiteley's process expert brought in mid year identified that as the major issue and calculated it needed closer to 7 MINUTES.
They had plant sitting outside capable of 4-5 minutes, but it was never installed. In 18 months these idiots burnt $34M and produced NOTHING of consequence, and what they did had a CoP inverse to the collective IQ of the Board & Mgt.