    RVR has been ramped up early.

    Thalanga Mine processing plant throughput has ramped up to annualised rate of 325ktpa

    • Mining and processing rates now exceed the design rate forecast in the Thalanga Restart Study (2015)

    • Ramp up completed ahead of schedule and approximately $1m under budget

    • Metallurgical recoveries and concentrate grades approaching Restart Study design parameters

    • 13,500 tonnes of low to medium-grade ore processed since production commenced with high grade ore now being blended into the mill feed as required

    • First concentrate deliveries will commence in the coming weeks and first cash flow is imminent thereafter.
 