    NSH,

    My take on the timing is a little bit different to yours though in the same ballpark. Assuming they have to flow back onto a pipeline. My timing is:

    Perforate - 1 day
    Frac setup - 2 days
    Frac - Max 3 days as is a vertical leg only
    Demob frac gear - 1 day
    Mobilise and tie in test separators - 2 days
    Flow back frac fluid - 5 days (Probably have to rock the well a few times)
    Allow flows to stabilise - 2 days
    Pressure build up and flow test - 2 days

    This outlook assumes a no result should be reported early, a delayed result is looking better.

    I have been in on this one for 2 ½ years and have already made a pretty nice profit. If this is the big one and it takes off I might just retire from the oil patch and just trade or invest in oil stocks.

    Cheers

    Jami
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
(20min delay)
Last
$2.77
Change
-0.020(0.72%)
Mkt cap ! $878.8M
Open High Low Value Volume
$2.78 $2.80 $2.76 $1.922M 691.0K

Buyers (Bids)

No. Vol. Price($)
2 2000 $2.74
 

Sellers (Offers)

Price($) Vol. No.
$2.81 4464 2
View Market Depth
Last trade - 16.10pm 18/07/2025 (20 minute delay) ?
DXI (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.