Goldies-Its a single shift!
You cant run numbers assuming they have no RDO's & make No allowance for
shutting operation down & restart each shift.
Better to do Calc's at 5hrs per day actual production producing hrs & imo
Just allow for 5 day per week & two RDO's should they only have one RDO
& actually achieve 5 1/2 hrs of production per day-in a 6 hr shift the great & we get surprised to the upside.
Remember safety checks & running out feed & pre plant feed commencement
do take a little time-plus there shift starts when they arrive on site-not when they
get to the plant -numbers still Calc well at 5 hrs p/d & 5 day's per week.
imo-gltah
salt
P.S- 50 tonner & 12 hrs shifts soon as implied by MGT.
- Forums
- ASX - By Stock
- OGX
- Target SP
Target SP, page-64
-
- There are more pages in this discussion • 62 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add OGX (ASX) to my watchlist
Currently unlisted public company.
The Watchlist
EL8
ELEVATE URANIUM LTD
Murray Hill, MD & CEO
Murray Hill
MD & CEO
Previous Video
Next Video
SPONSORED BY The Market Online