PRC has just released its Quarterly activities report (Friday 25/07/08). It clearly indicates that it does not expect to strike the coal seam until late August. The delay is because of the previously announced work at the pit bottom.
"The final 215 metre drive to coal commenced on 10 July 2008 and tunnel is presently at 2107 metres. Due to rescheduling of pit bottom concreting and construction works, the tunnel is now expected to intersect the coal seam on or around the end of August 2008."
- Forums
- ASX - By Stock
- PRC
- quarterly report out
quarterly report out
-
- There are more pages in this discussion • 3 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
AVH
Avita boosts skin restoration product portfolio with 'dermal matrix' – a kind of next-level gauze made of fake skin
STX
Strike hands $48.5M contract to Clarke Energy to produce 20x 4.5MW gas engines for Sth Erregulla
GML
Gateway Mining sells WA Eastern Montague gold project to Brightstar for $14M – half of that in shares