Hi, Sav..Agree totally with you on the GSG and HeN possible scenarios...It will most certainly have to be a multi rig programme if all of the forecast program is to even stand a chance of being met...
If the programme gets underway, say beginning of March and runs thru to the end of October, then that will afford some 8 months,or approx. 245 days of possible in-the-field working days....
8 conventional wells at,say, 40 days per well,(includes Mob. and Demob)=320 days..For all sorts of reasons, I would suspect that programme would not total 8 wells, but realistically, something like 6 wells, absolute maximum.(6x40=240),utilizing one Rig..No break-downs!! No downhole problems!! No time for contingencies...
Now the intriguing part...Some 40 CBM wells are proposed at say,30 days each,(includes Mob.& Demob.),
= some 1200 drilling days, divide by 245 available field days,= a minimum of 5 CBM rigs...
That would be a most intensive program in any company's workbook.. The logistics, alone, are mind-boggling...6 Rigs to "baby-sit'and crews to keep happy..Randy will be a busy boy!! Challenging, but possible...
- Forums
- ASX - By Stock
- CTP
- joint ventures
CTP
central petroleum limited
Add to My Watchlist
0.00%
!
5.5¢

joint ventures, page-17
Featured News
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
|
|||||
Last
5.5¢ |
Change
0.000(0.00%) |
Mkt cap ! $40.98M |
Open | High | Low | Value | Volume |
5.5¢ | 5.5¢ | 5.3¢ | $10.50K | 191.7K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 513796 | 5.3¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
5.5¢ | 100155 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 513796 | 0.053 |
3 | 556468 | 0.052 |
4 | 940000 | 0.051 |
3 | 500000 | 0.050 |
1 | 100000 | 0.044 |
Price($) | Vol. | No. |
---|---|---|
0.055 | 100155 | 1 |
0.056 | 15000 | 1 |
0.058 | 6030 | 1 |
0.059 | 326120 | 2 |
0.060 | 150000 | 2 |
Last trade - 16.10pm 22/07/2025 (20 minute delay) ? |
Featured News
CTP (ASX) Chart |