    I have had a look at the Company’s Yarrabubba opportunity and given they are promoting this as being “Low Entry Project” I thought I would spend the time to run the numbers below.


    Items to Consider:

    If they have to grind to 32um - the cost for capex and opex of milling will go way up - typically an exponential energy curve. My estimate is for a 75um grind.

    Very difficult to ship a material at 32 micron material realistically.

    In addition to high mining costs in a very tight pit, the long haul adds significantly mining costs - 21KM by the look of things.

    First few years would be expected to have much lower mass recovery - oxidised ore in LIMS, not considered in model.

    Would have to transport waste across Gazetted road as they have no place to put it on the site – not in model. This means huge costs transporting material from haul truck to quads and back to haul trucks – just not even practical.

    Model is most sensitive to Strip Ratio and mass recovery.

    Operating cost around $175/t – this is probably very conservative considering I didn’t add many of the other costs identified here because I don’t even have a comparison to try to estimate it.

    Concentrate is not likely to fetch more than $130.



    We need some luck with this as it seems a long shot.


    All IMO

    DYOR

 