Evil,
The last reference to the Kingaroy trial burn was in the investor presentation (28/4), which advised the burn would commence in June / July 2009.
The previous major update was in an announcement dated 3/4, which stated:
'At the Kingaroy site, work continues with the first of three process wells currently under construction, and with the groundwater monitoring stations now installed. Bids for the civil and mechanical contracts are to be received in two weeks, after which the detailed scheduling of site works, including finalisation of the expected Pilot Burn ignition date, can be completed.'
This leave a 7 week window, though as they say good things come to those who wait.