So reading the quarterly activities report it says the project will expect the first product during June.
How feasible is this?
From reading the other commissioning work/progress made it sounds like we won't get the first product till a bit later.
The piping and electrical seem a bit of a stretch to finish within 2 months.
A follow-on from this is that some equipment won't be commissionable until after the installations are made.