Ann: June 2021 Quarterly Activities Report, page-65

  1. 366 Posts.
    lightbulb Created with Sketch. 349
    Excelent progress in all fronts and good planing ahead !
    Not necessary negative, but I don't have the response to the below question:

    Does anyone knows if the nominal capacity (2mtpa) is considering 100% runtime ?, ( in the report they achieved 83% vs 85% forecast). If so, is this 100% run time achievable for this kind of processing plant ??

    I understand that the output depends on ore grade, recovery ratios, etc but I would expect to achieve 500,000t of ore/quarter processed, when we are mining around 600,000tons of ore per quarter ( last 2 quarters) , but ate not able to feed more than 420,000 tons per quarter. Hence my question.

    DFS quotes 314,000tpa os SC6, we are producing +77kt SC6 per quarter, which is 308ktpa, so we are close and improving...

    Have a nice end of the week.

 
watchlist Created with Sketch. Add PLS (ASX) to my watchlist
(20min delay)
Last
$2.80
Change
-0.030(1.06%)
Mkt cap ! $8.429B
Open High Low Value Volume
$2.81 $2.89 $2.79 $52.63M 18.65M

Buyers (Bids)

No. Vol. Price($)
23 263602 $2.80
 

Sellers (Offers)

Price($) Vol. No.
$2.82 8000 1
View Market Depth
Last trade - 16.10pm 06/08/2024 (20 minute delay) ?
PLS (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.