Have to love the recently updated (already incorrect, unattainable & outdated) timeline (Yes it was only published last week).
Although it does contain some glaring omissions......... Construction Start ? FCOT ? PLS Plant 6-12 months later ??
- Construction to start in Mid to late 2022 (Following finance and Detailed Engineering) - A 24 month minimum build for SC6 (Covid will say a more likely 30-36 month build) - FCOT likely for Q1 2025 - PLS plant 6-12 months later i.e. Q1 2026 - Ironing out of creases and issues at plant, build up to nameplate capacity in 2027 IMO
Rio Tinto seem to know a thing or two about mining and have recently published a very reasonable timeline, but hey DYOR
AVZ Price at posting:
19.5¢ Sentiment: Hold Disclosure: Held