At 17.5% complete they hadn't finished clearing out the building which was expected to take more than a week and be completed by August 16.
30th of August, clear out was complete and needed to provide critical information for Romball to carry out detailed engineering design work. 23%complete.
20 Oct.
Hole in the wall complete. Still an empty building. Still working on design work with Romboll. 33% complete.
Didnt Frank say look put for an update in a two weeks? Quite some time ago.
Anyway, next update at 60% less than 1 month after still having an empty building. Semi prodiction in less than 2 months.
sounds legit.
- Forums
- ASX - By Stock
- MNS
- $1 by EOY
MNS
magnis energy technologies ltd
Add to My Watchlist
0.00%
!
4.2¢

$1 by EOY, page-11
Featured News
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
|
|||||
Last
4.2¢ |
Change
0.000(0.00%) |
Mkt cap ! $50.37M |
Open | High | Low | Value | Volume |
0.0¢ | 0.0¢ | 0.0¢ | $0 | 0 |
Featured News
MNS (ASX) Chart |
Day chart unavailable