    Everything's fine with the Raisebore they have just encountered harder ground then anticipated during the second leg.
    With the first leg they rebuilt and replaced the cutters at the 250m mark and scheduled the same for the second. With the hardened ground on the second leg they have been replacing the cutters at the 100m marks and it takes about 5 days to lower, change cutters then raise to drill.
    So that being said on the 500m hole about a 25-30 day delay.
    The powers no big deal either, TasNetworks are responsible partly for the switch yard upgrade and they are owned by the Tasmania Government, and we all know how fast Government bodies move haha
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
(20min delay)
Last
58.0¢
Change
-0.015(2.52%)
Mkt cap ! $514.1M
Open High Low Value Volume
60.0¢ 60.0¢ 57.3¢ $1.166M 2.008M

Buyers (Bids)

No. Vol. Price($)
5 35405 58.0¢
 

Sellers (Offers)

Price($) Vol. No.
58.5¢ 238290 3
View Market Depth
Last trade - 16.10pm 31/07/2025 (20 minute delay) ?
MLX (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.