WKT 4.55% 10.5¢ walkabout resources ltd

Ann: Lindi Jumbo Project Update, page-13

  1. 6,025 Posts.
    lightbulb Created with Sketch. 852
    I guess the lack of resident downies today says it all! Great update by managment!

    * Processing plant civil works ~83% complete smile.png.

    * The Mine now has grid power with the Tanzanian Electrical Supply Company (TANESCO) completing installation of the 33kV powerline and the
    4.5MW line underway, just 3km short of the mining licence cool.png

    * Visually distinct high-grade graphitic ore zone (dark grey) within the starter pit area. The grade of the exposed graphite ore is estimated to be
    between 30% - 40% TGCeek.png

    * Preparation for construction of the retaining wall at the TSF is nearing completion biggrin.png

    What a pleasent sight:

    https://hotcopper.com.au/data/attachments/4492/4492305-fd63101fed877e5a7aeb80fcb811afad.jpg
 
watchlist Created with Sketch. Add WKT (ASX) to my watchlist
(20min delay)
Last
10.5¢
Change
-0.005(4.55%)
Mkt cap ! $70.48M
Open High Low Value Volume
11.0¢ 11.0¢ 10.5¢ $1.567K 14.9K

Buyers (Bids)

No. Vol. Price($)
4 296026 10.5¢
 

Sellers (Offers)

Price($) Vol. No.
11.0¢ 264758 8
View Market Depth
Last trade - 15.43pm 16/07/2024 (20 minute delay) ?
WKT (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.