They don’t finish them in order received (continued):
Another BLM Kingman Office project assigned to Paul Misiaszek. Mohave US Gold Exploration proposed to disturb as many as 93 acres by: • Constructing up to 600 drill sites with sumps (52 acres); • Constructing up to 17 miles (90,000 linear feet) of access roads (39.9 acres); • Constructing one laydown and storage area (0.9 acres); and, • Constructing up to two groundwater monitoring wells.
Application was made in April 2020. Environmental Assessment issued by BLM on May 23, 2022. Public comment period ended June 25, 2022. Approval issued by BLM on November 4, 2022. It has now become final 30 days later.
Native American concerns: “No concerns have been raised to date however the BLM and the Hualapai Tribe will continue consultation as needed throughout the exploration operations.” Eight tribes were consulted, including the Hualapai, Hopi and Navajo.
- Forums
- ASX - By Stock
- AZL
- AZL General Discussion
AZL General Discussion, page-13743
-
- There are more pages in this discussion • 8,657 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add AZL (ASX) to my watchlist
(20min delay)
|
|||||
Last
2.0¢ |
Change
-0.002(9.09%) |
Mkt cap ! $89.47M |
Open | High | Low | Value | Volume |
2.1¢ | 2.1¢ | 1.9¢ | $63.75K | 3.165M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 291133 | 2.0¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
2.1¢ | 2171592 | 7 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 291133 | 0.020 |
19 | 4314134 | 0.019 |
29 | 5178183 | 0.018 |
26 | 5201348 | 0.017 |
16 | 4581768 | 0.016 |
Price($) | Vol. | No. |
---|---|---|
0.021 | 1962989 | 6 |
0.022 | 6645367 | 11 |
0.023 | 3536175 | 6 |
0.024 | 2510822 | 16 |
0.025 | 4410617 | 14 |
Last trade - 16.10pm 19/07/2024 (20 minute delay) ? |
Featured News
AZL (ASX) Chart |