Yes I am optimist, particularly with stocks I invest in.
If they finish everything at Vali by the end of February, it would have taken then them about 5 months from when they started the site works which was around mid September.
When they announced the commencement of construction in mid September, they were expecting Vali to be in production by December, that's only about 3-3.5 months.
With Odin they started mid December, with no rain delays, having only one well and with only 1.4 kms of pipeline, they should be able to comfortably finish it in 4 months, that will take them to around mid April.
Hopefully, they have learned a few things from Vali and will be able to reduce any delays and streamline the process.
IMO second time around management have a taken a conservative approach to their time estimates for Odin.
- Forums
- ASX - By Stock
- MEL
- Ann: Vali and Odin Update
MEL
metgasco ltd
Add to My Watchlist
0.00%
!
0.2¢

Ann: Vali and Odin Update, page-121
Featured News
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
|
|||||
Last
0.2¢ |
Change
0.000(0.00%) |
Mkt cap ! $3.665M |
Open | High | Low | Value | Volume |
0.2¢ | 0.2¢ | 0.2¢ | $2.284K | 1.142M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
10 | 19005694 | 0.2¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
0.3¢ | 11409690 | 13 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
10 | 19005694 | 0.002 |
7 | 34000999 | 0.001 |
0 | 0 | 0.000 |
0 | 0 | 0.000 |
0 | 0 | 0.000 |
Price($) | Vol. | No. |
---|---|---|
0.003 | 6059665 | 11 |
0.004 | 10479052 | 6 |
0.006 | 311675 | 1 |
0.020 | 15085 | 1 |
0.022 | 91666 | 1 |
Last trade - 16.10pm 27/06/2025 (20 minute delay) ? |
Featured News
MEL (ASX) Chart |
The Watchlist
PAR
PARADIGM BIOPHARMACEUTICALS LIMITED..
Paul Rennie, MD & Founder
Paul Rennie
MD & Founder
SPONSORED BY The Market Online