Ann: Wolfsberg Project Definitive Feasibility Study Results, page-4

  1. 921 Posts.
    lightbulb Created with Sketch. 2227
    Well here it finally is. Ouch. $873m capital cost estimate.

    This DFS is based on a hydroxide sale price of $48,600/t also which is far less conservative than most other PFS/DFS. The cost to produce per tonne is high also.

    Classic TS BS to boot: "Construction of downstream project facilities expected Q4, 2023."

    So they're saying hydroxide refinery construction will start this calendar year? Right

    Good to finally see some numbers though..


    Last edited by Vodski: 08/03/23
 
watchlist Created with Sketch. Add EUR (ASX) to my watchlist
(20min delay)
Last
5.2¢
Change
-0.002(3.70%)
Mkt cap ! $76.89M
Open High Low Value Volume
5.7¢ 5.7¢ 5.2¢ $36.44K 649.5K

Buyers (Bids)

No. Vol. Price($)
3 241391 5.2¢
 

Sellers (Offers)

Price($) Vol. No.
5.7¢ 63228 1
View Market Depth
Last trade - 11.22am 28/06/2024 (20 minute delay) ?
EUR (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.