@KDMT Rainy season in CDI usually considered June-Oct , so effects Q2 slightly and Q3 majorly. main problem is ore handling for the mill, with wet sticky oxide material clogging transfer chutes, feeders, and mill feed chutes. plus making Mining difficult in the pit. Roads untrafficable for haul trucks, flooded access etc. as the pit develops into fresh material, these problems become easier to handle. Year 1 generally the worst.