In March, STX estimated it'd cost $19.2m.
Now it comes in at $30m.
Is this material for a $1bn company? Probably not.
However - as a shareholder I would have appreciated an announcement saying that construction is running slower than expected and is going to cost more.
On the bright side, learning these lessons with Walyering is much cheaper than making the mistakes with SE.
- Earlier permitting
- Offshore fabrication
- Traditional EPC rather than inhouse
- Forums
- ASX - By Stock
- STX
- Ann: Walyering Production Update
Ann: Walyering Production Update, page-21
-
- There are more pages in this discussion • 279 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add STX (ASX) to my watchlist
(20min delay)
|
|||||
Last
23.0¢ |
Change
0.020(9.52%) |
Mkt cap ! $659.0M |
Open | High | Low | Value | Volume |
21.5¢ | 23.0¢ | 20.8¢ | $2.859M | 12.94M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
6 | 226888 | 22.5¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
23.0¢ | 4366669 | 32 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
6 | 226888 | 0.225 |
5 | 380000 | 0.220 |
8 | 878892 | 0.215 |
14 | 1340308 | 0.210 |
31 | 1224333 | 0.205 |
Price($) | Vol. | No. |
---|---|---|
0.230 | 3809669 | 31 |
0.235 | 738380 | 17 |
0.240 | 1313046 | 16 |
0.245 | 678188 | 14 |
0.250 | 2059188 | 27 |
Last trade - 16.10pm 04/10/2024 (20 minute delay) ? |
Featured News
NEWS
Antler Copper Project hits major permitting milestone – air quality permit advances to final review
STX (ASX) Chart |