Yes Gammat,
That is correct, severe delays on the backup generators.
"The full planned electrical capacity (including backup generators) is necessary before the commissioning team will feed ore through the entire processing circuit.""
Keep on pumping the success on being well behind schedule. WKT was meant to be producing its first concentrate as of today, yet they have only finished 1 of 4 sections of the plant.