    There appear to be two pieces of equipment there: one on skids, and one in the container. The one on skids looks like a production unit, whereas the other one looks like a test unit. Is that correct?

    I am not an oiler, but the size of the one on skids is rather large (similar ones I can find online range from 2000 bpd up to 7000 bpd). I wonder whether AP is keeping his cards very close to his chest on this: are that THAT confident that Marti is THAT good?

    The timeline is roughly correct: 176 metres into the new section, over almost 5 days (35m/day is about the same pace) as casing finished up mid last week (and these pics appear to be taken about 6 hours ago, based on the shadow / direction etc., which means they were taken Monday afternoon in Cuba). So the timeline adds up (i.e. there was no delay caused by the equipment - so perhaps it was scheduled to arrive now anyway?).

    Kit.
 
watchlist Created with Sketch. Add MAY (ASX) to my watchlist
(20min delay)
Last
3.2¢
Change
0.001(3.23%)
Mkt cap ! $107.8M
Open High Low Value Volume
3.1¢ 3.3¢ 3.1¢ $109.4K 3.396M

Buyers (Bids)

No. Vol. Price($)
2 285693 3.2¢
 

Sellers (Offers)

Price($) Vol. No.
3.3¢ 2114263 9
View Market Depth
Last trade - 16.10pm 26/09/2024 (20 minute delay) ?
MAY (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.