Hi Galliumaslan,
I guess it depends on the scale of the plant, and also the scale and grade of the mine.
DEG’s Hemi is on track to be producing in 2026, only 6 years post-discovery.
![]()
GOR’s Gruyere mine was discovered in 2013, construction started in 2017 and first gold production in 2019 so 6 years as well.
Now you might say niobium is different. Entirely different chemistry and processing etc. But what we have is the scale and grade. We don’t need a ridiculously large plant. 1.5-2Mtpa because our ore is very high grade. I expect CAPEX and OPEX to be low. Remoteness might be an issue but as the MD says, it will be forgiven by our grade.
- Forums
- ASX - By Stock
- WA1
- General discussion
General discussion, page-7529
-
-
- There are more pages in this discussion • 2,823 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add WA1 (ASX) to my watchlist
|
|||||
Last
$17.16 |
Change
0.090(0.53%) |
Mkt cap ! $1.071B |
Open | High | Low | Value | Volume |
$17.20 | $17.57 | $16.65 | $9.930M | 580.8K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 50 | $17.16 |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
$17.19 | 500 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 50 | 17.160 |
1 | 733 | 17.140 |
1 | 503 | 17.130 |
1 | 556 | 17.110 |
1 | 500 | 17.100 |
Price($) | Vol. | No. |
---|---|---|
17.170 | 81 | 1 |
17.180 | 134 | 1 |
17.190 | 500 | 1 |
17.200 | 500 | 1 |
17.230 | 936 | 3 |
Last trade - 16.10pm 12/07/2024 (20 minute delay) ? |
Featured News
WA1 (ASX) Chart |