Update – Thursday 2 May 2024
Reports today that tunnel boring machine (TBM) Florence has stopped tunnelling are incorrect.
TBM Florence remains fully operational and is now more than 800 metres into excavation of the Snowy 2.0 headrace tunnel at Tantangara. The TBM has operated successfully since its restart on 8 December 2023 and has moved through identified soft ground into hard rock.
The total distance tunnelled by all three Snowy 2.0 TBMs across the pumped-hydro renewable energy project is approximately nine kilometres.
https://www.snowyhydro.com.au/news/snowy-2-0-project-update-april-2024/