Best timeline I'd guess, post EPA/Ministerial approval:
Formal offtakes 3-6 months
Finance +3mnths after offtakes
Final design and procure, confirmed transport/port contracts, etc in parallel with offtakes and finance, ready for signing
->DFS/FID
Completed production trials and optimisation, recruitment
Production start-up 3-6 mnths
=> prodn in 12-15 mnths from Ministerial approval
The last presso said construction in 6-8mnths from final approvals.
I'd include EPA/Minister/offtakes/finance/final DFS/FID all complete as "approvals" before that 6-8months starts, so consistent with the above
rerates with
approval
offtakes
finance
FID
prodn/cashflow and ramp up
Muchea progress
- Forums
- ASX - By Stock
- VRX
- Long suffering holder
Long suffering holder, page-177
-
- There are more pages in this discussion • 14 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add VRX (ASX) to my watchlist
(20min delay)
|
|||||
Last
4.0¢ |
Change
-0.002(4.76%) |
Mkt cap ! $25.13M |
Open | High | Low | Value | Volume |
4.0¢ | 4.0¢ | 3.8¢ | $14.44K | 367.6K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 24730 | 3.8¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
4.0¢ | 161294 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 24730 | 0.038 |
1 | 135054 | 0.037 |
3 | 30500 | 0.036 |
2 | 33000 | 0.035 |
2 | 129410 | 0.034 |
Price($) | Vol. | No. |
---|---|---|
0.040 | 161294 | 1 |
0.041 | 61541 | 1 |
0.042 | 20079 | 1 |
0.043 | 41293 | 2 |
0.044 | 140000 | 2 |
Last trade - 16.10pm 20/06/2024 (20 minute delay) ? |
Featured News
VRX (ASX) Chart |
The Watchlist
HAR
HARANGA RESOURCES LIMITED.
Peter Batten, MD
Peter Batten
MD
Previous Video
Next Video
SPONSORED BY The Market Online