    A very simple rule of thumb which I typically use when evaluating timeframes (my background is large construction projects) is that a best case scenario is for a company to spend an average of $1M day on construction activities. Then add additional time for feasibility studies, engineering (50-100% of the construction timeframe)

    Therefore applying this to other projects results in the following:

    * Arafura - BFS complete end of 2012
    - Allow 6 months decision to mine, contracting, financing etc (ambitious but doable if they get their ducks lined up - June 2013
    - ~$1B costs - Lets assume 80% of these are direct construction. Therefore 800 days construction - 2 years Therefore assume min 1yr engineering - June 2014
    - 2 years construction and you get to the mid-2016 before commissioning and operation, assuming everything goes well and you don't have any delays. To me 2017 would be more likely.

    * Alkane - BFS complete end of 2011 (being conservative from their recent announcements)
    - Allow 6 months financing etc - June 2012
    - ~$500M costs (until they confirm throughput this is just a guess). Assuming $400M relate to construction or 1 1/2 years. I year engineering - June 2013
    - 1 1/2 years construction - end 2014

    Chihawk can update on Moly, but assuming assuming a $600M capital spend they are still looking at about 2 years construction, when they have finished their engineering to an acceptable level, and who knows when this is.

 
watchlist Created with Sketch. Add LYC (ASX) to my watchlist
(20min delay)
Last
$6.37
Change
-0.190(2.90%)
Mkt cap ! $5.954B
Open High Low Value Volume
$6.53 $6.55 $6.35 $21.07M 3.291M

Buyers (Bids)

No. Vol. Price($)
6 11945 $6.36
 

Sellers (Offers)

Price($) Vol. No.
$6.37 99 1
View Market Depth
Last trade - 16.10pm 08/07/2024 (20 minute delay) ?
LYC (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.