First stope ore could be pushed back to Q2 FY25 due to flood-like event: Aurelia


Aurelia Metals (ASX:AMI) has confirmed underground development works recommenced in early July after a flood-like water damage event at Federation.

However, the production of first stope ore could be pushed back to Q2 of FY25, the company warned on Friday.

This comes despite 24/7 rostering back in place per Aurelia’s Friday update; a water treatment plant has also been brought on-site to further assist with dewatering both incidental and natural in the job.

In June, the company flagged its NSW-based project had been subject to heavy rains across multiple months of early CY24, culminating in a pause of underground works.

Four water evaporator assets were installed at the Hera tailing storage facility which Aurelia described as part of long-term water management.

“It is pleasing that development at Federation has recommenced and returned to 24 hour operation,” CEO Bryan Quinn said.

AMI last traded at 21.5cps.