    • Release Date: 08/05/12 13:07
    • Summary: GENERAL: MRP: CONSTRUCTION OF NGATAMARIKI GEOTHERMAL PLANT GAINS MOMENTUM
    • Price Sensitive: No
    • Download Document  4.15KB
    					
    
    MRP
    08/05/2012 11:07
    GENERAL
    
    REL: 1107 HRS Mighty River Power Limited
    
    GENERAL: MRP: CONSTRUCTION OF NGATAMARIKI GEOTHERMAL PLANT GAINS MOMENTUM
    
    The arrival of a major shipment to Mighty River Power's Ngatamariki
    geothermal development over the last week marked a significant milestone in
    the construction of the Company's 82MW plant.
    
    The shipment of the towers for the air cooling system, from international
    geothermal technology supplier ORMAT, weighed more than 2,000 tonnes and
    arrived in New Zealand at the Port of Tauranga. Approximately 90 truckloads
    of equipment were delivered on site over the last week. The cooling system is
    made up of four structures that, at approximately 15 meters high and 300
    meters in combined length, represent a significant physical aspect to the
    plant.
    
    Mighty River Power's General Manager Development, Mark Trigg, said delivery
    of the shipment was an important milestone in the construction of the plant
    and would enable future works to continue on the original construction
    schedule. The cooling system plays an integral role in the operations of the
    plant.
    "It's great to see the progress on site.  The foundations for the cooling
    towers are almost complete and very soon we'll be able to see the station
    really begin to take shape.  We remain on schedule for completion and
    commissioning in mid 2013," said Mr Trigg.
    
    The Ngatamariki plant, the third major geothermal power station constructed
    by the Company over the past 5 years, will provide additional renewable base
    load capacity and further diversify the Company's generation portfolio.
    Mr Trigg said the plant would complement the Company's core hydro base,
    lifting Mighty River Power's geothermal energy production (measured on
    ownership interests) from over 30% to approximately 40% of the Company's
    generation output, and taking total geothermal capacity under its operation
    above 460MW.
    
    The development, which follows the commissioning of Kawerau (2008) and Nga
    Awa Purua (2010), will be 100% owned by Mighty River Power, although Tauhara
    North No.2 Trust - which was a joint participant in securing the resource
    consents - would receive a revenue stream from the project and has an option
    to take an equity stake in the plant at market value no earlier than 10 years
    after final commissioning.
    
    ENDS
    
    Notes to Editors:
    
    o The Ngatamariki geothermal steam field is located 17kms north-east of Taupo
    
    o The project cost of NZ$466 million is financed from the Company's balance
    sheet. In mid 2011, the Company secured $250 million additional debt
    facilities to supplement existing debt capacity
    
    o ORMAT was awarded the Ngatamariki project under an EPC (Engineering,
    Procurement and Construction) arrangement. As a turn-key contract, this
    significantly reduces construction risk of the power plant  to Mighty River
    Power. Responsibility for steamfield work remains with the Company.
    
    o ORMAT's modular design for the development allows four generation units to
    be built in its first phase, with infrastructure capacity sufficient to allow
    for further units to be added in the future
    
    About Mighty River Power
    
    Mighty River Power is an integrated electricity generator and retailer, and
    New Zealand's only large renewables dominated energy company with both hydro
    and geothermal generation. Our core business is based on reliable, low fuel
    cost generation, complemented by electricity sales to businesses and homes
    through multiple retail brands.
    
    The Company's sales to major industrial and commercial users and through our
    retail brands, Mercury Energy, GLO-BUG, Bosco Connect and Tiny Mighty Power,
    account for about 18% of New Zealand's total electricity consumption.
    
    More than 90% of our generation is from renewable sources, with a substantial
    geothermal share, supported by a flexible gas-fired plant in Auckland. Mighty
    River Power is among the world's top 10 geothermal businesses and is
    investing through GeoGlobal Energy in geothermal developments in the US,
    Chile and Germany.
    
    Mighty River Power won Overall Energy Company and Project of the Year at the
    2010 Deloitte Energy Excellence Awards and in 2011 was named Energy Retailer
    of the Year (Mercury Energy).
    End CA:00222624 For:MRP    Type:GENERAL    Time:2012-05-08 11:07:58
    				
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.