Hi All,
We know it costs about $4.00 to sand mine a tonne of alluvium to get at least a kilo of TREO worth at the end of the process $47. Even if it took a 1000 tonnes of alluvium to get 1 tonne of TREO that tonne would only cost $4000.
The dry processing will probably cost about $25 tonne to achieve the a one tonne of of dry processed concentrate not for each tonne processed.
Finally, to achieve the final mixed bag $5,000 a tonne to produce a finished material by chemical processing. No thorium or uranium.
Look at each step and add up the cost:
Wet processing:-----------------------$4000
Dry processing:-------------------------$25
Chemical processing:------------------$5,000
Total:-------------------------------$9,025
Value:------------------------------$47,000
The way I see it, there is a substantial profit in exploiting the CUX resource and I mean SUBSTANTIAL.
DYOR
Cheers
- Forums
- ASX - By Stock
- ENV
- race to the finish line
race to the finish line, page-55
Featured News
Add ENV (ASX) to my watchlist
(20min delay)
|
|||||
Last
1.1¢ |
Change
0.000(0.00%) |
Mkt cap ! $10.53M |
Open | High | Low | Value | Volume |
1.1¢ | 1.1¢ | 1.1¢ | $8.846K | 804.8K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
6 | 2724404 | 1.0¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
1.1¢ | 909090 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
6 | 2724404 | 0.010 |
10 | 1991444 | 0.009 |
6 | 3748500 | 0.008 |
6 | 1607857 | 0.007 |
3 | 1266666 | 0.006 |
Price($) | Vol. | No. |
---|---|---|
0.011 | 909090 | 1 |
0.012 | 2219200 | 7 |
0.013 | 5977210 | 7 |
0.014 | 1406099 | 5 |
0.015 | 2182210 | 8 |
Last trade - 12.45pm 12/07/2024 (20 minute delay) ? |
Featured News
ENV (ASX) Chart |