In regard to what I just posted:
"Section 4.10 then states that the cost is likely to be nearer to $3.50-$5 per tonne moved. I gather this is just the cost of moving the waste/overburden? This isn't the cost of mining the ore right?"
I think I get it... so if there is a 1:1 overburden to ore ratio, then @$16/t the cost of mining the ore is 2x$16t or $32/t. So this means that it could potentially come down as low as $7/t - $10/t ore under a cheaper contractor?