Once TD has been reached at 9400ft, it can take ~ 12hrs to pull the string from the hole, more likely 24-36hours if they decide to run wiper trips and circulate to clean up the wellbore before pulling out to run logs. Then depending on the suite of logs, 24-48 hours to rig up & run wireline in the hole, run logs and pull out. Results should be available fairly quickly onsite. So conservatively, 4 days between TD and prelim log results I reckon.