    For those about to punt...

    Power issues to rig remain unresolved (perhaps 5-7 days to sort) - worst case = mobilize another rig...

    Drill stem stuck @ 1000m not salt-related.
    My understanding of plan is to re drill from surface to recover stem in hole below 1000m...then continue on.

    Estimates 4-6 wks to complete (assuming no new rig needed)

    GM hole cost now estimated $20-$25m...

    NSE liable for anything over $13m (any recovery from rig contractor notwithstanding).

    Anatol - background gas very +ve... over ridden in short term by ultra -ve sentiment due to recent shock.

    Slampoil - your understanding?

    GLTA

 