$3m CAPEX for Pearse? I've never seen that.. They want to rebuild the gold circuit at the plant and as Pearse is open cut it will also need a pre-strip. Would $3m be sufficient for that?
KBL's October 2012 fact sheet talks about $15m which seems to include gold circuit, SOZ/ESOZ refurbishment, Pearse pre-operations, paste fill and tailings dam.
Seeing as the tailings dam is apparently already being built and paste fill relates to filling underground voids (which relates to current ops), if $3m was all that is required for Pearse then they will have spent a hell of a lot of the $15m. For this reason, $3m is probably not the number, but happy to hear your source.
Raising any money is difficult, and doing it anytime over the past year would be difficult. That was what I meant with my peer comparison.
- Forums
- ASX - By Stock
- KBL
- mineral hill operations update
mineral hill operations update, page-15
-
- There are more pages in this discussion • 8 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add KBL (ASX) to my watchlist
Currently unlisted public company.
The Watchlist
LPM
LITHIUM PLUS MINERALS LTD.
Simon Kidston, Non--Executive Director
Simon Kidston
Non--Executive Director
SPONSORED BY The Market Online