I posted earlier on
"I suppose all is not lost since Starfish-1 would have cost less than the budgeted $80M . Stena Drillmax has been released after about 25 days of a planned 35 day drill. That would save 10 days at $560K/day ($5.6M). Then there would be a saving in wages for the 360(?) crew - $2M (?) plus accommodation charges. Maybe a total of $10M (?)"
I think the original budget was $80M