    PERKOA PROJECT UPDATE – MAIDEN DELIVERIES TO PORT
    KEY POINTS
    ? Approximately 17,000 tonnes of zinc concentrate stockpiled at the mine.
    ? Trial trucking of concentrate to port commenced - 120 tonnes now at port.
    ? Installation of second ball mill (to achieve 1 million tonne throughput)
    with the second stage ramp-up in production to start during Q4 CY2013.
    Blackthorn Resources Limited (ASX: BTR) (“the Company” or “Blackthorn Resources”)
    wishes to provide the following update regarding the Perkoa Mine in Burkina Faso, West
    Africa.
    The Perkoa Project is a joint venture between Glencore Xstrata, Blackthorn Resources
    and the Burkina Faso Government which has developed the first large-scale base metals
    mine in the country. The project is located 120km west from the capital Ouagadougou.
    Glencore is the Project Manager.
    Operations
    First deliveries of concentrate
    The first deliveries of saleable product were recently made to the Port of Abidjan in Cote
    d’Ivoire as part of a process of testing the logistics chain from the mine to the port prior to
    embarking on full-scale transport of concentrate.
    Photographs below show stockpiling of 120 tonnes of zinc concentrate at the port.
    The first shipment of export sales is likely to contain 13,000 tonnes of zinc concentrate
    and is expected to be loaded early September 2013.
    Process Plant
    Ore throughput and concentrate quality are approaching design specifications for a single
    ball mill operation.
    The plant milled 50,739 tonnes of ore in June 2013, with plant availability at 93.3% and an
    average throughput of 75.6 dry metric tonnes per hour.
    Zinc recoveries and concentrate grades continue at close to target levels.
    The key production statistics are provided in the Table below.
    2
    June 2013 YTD
    MATERIAL HANDLED
    ROM (t) 59,000 223,272
    Tonnes Milled (t) 50,739 231,000
    Zn Feed Grade (%)* 5.02 4.57
    Pb Feed Grade (%) 0.46 0.52
    * Zn ore predominantly from open pit mining
    The installation and commissioning of the second ball mill is expected to be completed in
    Q4 CY2013, enabling ramp-up to 1.0 million tonne throughput capacity.
    Open Pit
    Mining in the open pit is continuing, with the second push-back now well under way.
    Drilling performance in June was on target following the introduction of an additional drill
    rig. This follows the below budget drilling performance in April and May 2013 due to the
    poor availability of the rigs. As a result, production from the open pit is below budget yearto-
    date, however this is being offset by better production and grades from the
    underground mine.
    A new drill contractor is now in the process of mobilising to site to ensure drill performance
    continues to improve.
    Underground
    Underground ore production from development was ahead of target in June 2013, with
    high-grade development ore of approximately 13.5% Zn being mined. This ore is being
    used to improve the head grade of the feed to the process plant. Stoping from the 130
    level is expected to commence in July 2013, which will provide increased production
    tonnage and grade from the underground mine.
    The Main Ramp is progressing well following the completion of ventilation raises to the
    160 and 190 levels.
    Managing Director Scott Lowe said:
    “The first delivery of saleable product to port is another important milestone at
    Perkoa and we look forward to the loading of the maiden shipment in the near
    future. We are also looking forward to continuing ramp up at the mine.”
    Should you require further information please contact:
    Scott Lowe
    Managing Director
    Ph: + 61 2 9357 9000
    3
    Figure 1 – Loading concentrate at Perkoa Mine
    Figure 2 – Trucking concentrate
    4
    Figure 3 – Unloading at Port
    Figure 4 – Concentrate at Port
    5
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
(20min delay)
Last
48.5¢
Change
-0.010(2.02%)
Mkt cap ! $280.9M
Open High Low Value Volume
49.5¢ 50.0¢ 48.0¢ $867.4K 1.770M

Buyers (Bids)

No. Vol. Price($)
1 2212 48.5¢
 

Sellers (Offers)

Price($) Vol. No.
50.0¢ 39014 3
View Market Depth
Last trade - 16.10pm 18/09/2025 (20 minute delay) ?
BTR (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.