I had a read of the 2012 Annual Report to remind myself of some of the dates that were published then.
End January 2013 - Completion of commissioning of the crusher
Late 2013 - Processing plant expected to be commissioned
Late 2013 - Production from Rocklands is due to commence
Early 2014 - Rail Load out facility complete
I wonder how we are progressing against these items?
I also noted that the share price at the time of going to press was $4.77 with a market cap of $890 million which was sated to be undervalued.
-