'Currently, the Enerdrill Rig #3 (Rig #3) is in Mandurah, Western Australia, undergoing a series of final
operations testing, which is expected to be finalised by mid-October.'
'Enerdrill has been communicating regularly with New Standard about the progress of its preparations
and New Standard has been regularly reviewing the rig’s test results, mobilisation and rig-up schedules
and operational plans,” Mr Thick said.
As part of the contract compliance requirements, a third party technical audit is scheduled to be
conducted on Rig #3 in October. Once the audit process is finalised, Rig #3 will be mobilised to site. It is
anticipated that once on site at Condon-1, the rig will take approximately ten days to complete the rigup.'
So do we assume the spud would be mid to late November?