I thought that may have happened (no ore in the sheds) when they had the run of 4 ships in 4 days after the last big weather event, but i don't belierve it did - got close (correct me if i am wrong)
Assuming the shed had 225k after the last long weather event. Starting (Great Rich) on 29/9/13 after a delay 1 ship in 13 days
4 ships in 4 days supply Shed -240k +112 = 127k
1 day supply no ship +28 = 155k
3 ships 3 days 3 days supply -180 +84 = 59k
No ships ( I believe that is because of swell, no ships in port) 3 days supply (including today) +84 Shed = 143k
Undoubtedly there will be times when the shed can't cope, I dont think it will effect their ability to get 10mt out.
- Forums
- ASX - By Stock
- GBG
- 3q'13 financial results
3q'13 financial results, page-5
-
- There are more pages in this discussion • 28 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add GBG (ASX) to my watchlist
Currently unlisted public company.
The Watchlist
RCE
RECCE PHARMACEUTICALS LTD
James Graham / Dr Alan Dunton, MD & CEO / Non-Executive Director
James Graham / Dr Alan Dunton
MD & CEO / Non-Executive Director
SPONSORED BY The Market Online