    if weather conditions prevent shipping on any particular day(about 30 days/year)there is no need to catch up or a need for a mooremaster, there is enough days in a year to ship out 8mtpa.

    strictly speaking there is no need for a storage shed as the train capacity 28kt/day is sufficient to load a ship in half a day. (JUST IN TIME PLUS)

    KARARA PROJECT CAPACITIES
    production = 24kt/day
    trains = 28kt/day
    ship loader 120kt/day
    ship capacity = 60kt
    shipping days = 327 = 19.6mt/pa
 