    In general terms the company that supplys and makes the DMS commision the machine themselves and loms chief engineer generaly does a working coarse on trouble making/fixing,parts managment and so on,then its ticked off and LOM take over.
    The same when i buy bottling lines,printing presses and so on,i guess its the same here.
    Machines and commisioning are always signed off and workable when the coy's engineer is at a competant level or they are charged for each day there after.
    I would not expect the DMS to not be running by 1 week,2 the most.
    Dazzaa the wise one,and all knowing of things that make the universe calm.
 
watchlist Created with Sketch. Add LOM (ASX) to my watchlist
(20min delay)
Last
3.5¢
Change
-0.003(7.89%)
Mkt cap ! $10.15M
Open High Low Value Volume
3.8¢ 3.8¢ 3.5¢ $7.985K 219.1K

Buyers (Bids)

No. Vol. Price($)
1 2000 3.6¢
 

Sellers (Offers)

Price($) Vol. No.
4.0¢ 20000 1
View Market Depth
Last trade - 13.38pm 10/09/2024 (20 minute delay) ?
LOM (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.