    KEY OUTCOMES
    The key findings of the
    June 2013
    Scoping Study report are summarised below, based upon a
    conceptual
    mining and processing operation of
    1,200,000 tonnes of ore per annum.

    Estimated
    initial
    capital cost of US$91.6 million which
    includes
    contingencies

    Estimated average mine gate cost of pro
    duction US$101.58 per tonne

    Free on Board cost (FOB)
    Port of Pemba
    estimated at an average of US$198.01 per tonne

    Peak development cost funding requirement of US$69 million

    Payback period within 6 months of commission
    For

    Says it all really with Graphite @ $1300 per tonne!!!