    Operating Update – Post Flooding Events

    • Interim mining operations, pit water pump outs and transition towards
    recommencement of full mining activities are all proceeding in line with the details
    of the ASX announcement of 20 February 2014.
    Garden Well
    • All external flood bunds have been reinstated and bolstered as required.
    • Pump out of the Garden Well pit (north stages 1-3) by expert contractor
    commenced a week ago and is ramping up to full pumping capacity in the next few
    days. Pump out progressing in line with details given in previous announcement.
    • Mining in the southern part of the pit (stage 4) has recommenced and is expected
    to return to full day and night shift mining today. Grade control and blasting have
    recommenced. Minimal ore supply has been generated to date but will increase
    over the coming week.
    • The mill has been running since the flood at approximately 5 million tonnes per
    annum, treating ore from ROM stockpiles.
    Rosemont
    • All external flood bunds have been reinstated and bolstered as required.
    Abandonment bunds will be raised when mining commences to provide suitable
    waste rock.
    • Pump out of the Rosemont North open pit has been completed with only small
    areas of standing water now required to be removed. The level of sediment on the
    pit floor is estimated at approximately 100mm, which is in line with the Company’s
    pre-pump out expectations.
    • Mining options for the silt and the first 2 metre ore flitch in the Rosemont North Pit
    are being assessed at present and mining will commence as soon as practicable.
    • Mining of waste in the Rosemont Main pit commenced a week ago and is
    expected to ramp up to full day and night shift mining in several days. Mining of
    ore in the Main Pit is expected to commence in around 2 weeks once sufficient
    grade control drilling and assay analysis is completed.
    • The mill has been running since the flood at approximately 1.6 million tonnes per
    annum, treating ore from ROM stockpiles.
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
(20min delay)
Last
$4.42
Change
0.120(2.79%)
Mkt cap ! $3.340B
Open High Low Value Volume
$4.35 $4.47 $4.35 $17.36M 3.934M

Buyers (Bids)

No. Vol. Price($)
1 4000 $4.42
 

Sellers (Offers)

Price($) Vol. No.
$4.43 5229 2
View Market Depth
Last trade - 16.19pm 22/07/2025 (20 minute delay) ?
RRL (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.